To some activists it also symbolizes the tense relations between Israeli settlers and Palestinians.
Designed by the Spanish architect’s
Zurich-based firm Calatrava Valls SA, the curving bridge is part of a
13.8-kilometer light rail line now under construction. The bridge’s
slender steel pylon, which soars 118 m above one of the city’s busiest
intersections, sits adjacent to a future underground train station for
the new Jerusalem and Tel Aviv line. A consortium called Citypass has a
28-year build-operate-transfer contract for the project. It includes
French firms Alstom and CGEA Connex, and Israel’s Polar Investments,
Harel Insurance and local civil engineering firm Ashtrom. “This is a
once-in-a-lifetime proj-ect from an engineering standpoint, with
unprecedented international involvement,” says Tzachi Strasser, a civil
engineer with Israel’s Gadish Group, project manager on behalf of the
client, Moriah, Jerusalem’s municipal-owned development firm.
 |
|
Steel sections are placed at night
|
But that also includes international
controversy. France’s Alstom and CGEA Connex are being sued by a
pro-Palestinian group in a French court, who say the line serves Jewish
settlers living on land “stolen” from Palestinians. A CityPass
spokesman contends that the line will serve all residents of Jerusalem
and says the issue of Irish unions refusing to train Israeli rail
workers is “very insignificant.”
The bridge is designed to cut an
S-shaped curve between Jaffa Road and Herzl Boulevard in Jerusalem. A
glass embankment running along the bridge’s eastern side will serve as
a pedestrian walkway. “This is the first [cabled-stayed] bridge with a
curvature of 90° ever built for use by light rail,” says Dan Ben-Amram,
planning manager for Moriah. “Initially, Calatrava had proposed using
welded steel plates to link the vertical and horizontal parts, but we
decided to opt for steel casting on the advice of Cimolai.”
Italy-based Cimolai Technology SPA is one of the span’s deck
manufacturers on behalf of the contractor, a joint venture of Israel’s
Koors Metals and Ramet Ltd.
Cimolai is welding the two deck
sections at either end of the bridge. The end sections are 15 m wide,
30 m long and 200 millimeters thick, and are curved to create the
bridge’s sinuous profile.
Cimolai also is manufacturing the
pylon, located in the middle of the S curve, in 12 sections of about 10
m each. Each segment is welded on site using steel plate up to 200 mm
thick with full penetration welds.
 |
|
Calatrava's design calls for an asymmetrical pylon and harp-like cables
|
The bridge sits on concrete supports
at either end. These are supported by concrete foundations drilled
using the largest micropile available in Israel. Crews drilled some 70
holes, each with a radius of between 60 to 90 centimeters, to depths of
25 m, Ben-Amram says.
Workers are placing 70 cables that
give the bridge its harp-like appearance. Thirty-three are connected
to one side of the deck, with an equal number linked to the southern
steel concrete support. The four largest cables are connected to the
steel pylon’s base to provide balance. With placement of four to six
“strings” per night, officials predict that construction will finish by
late August. Then France’s Alstom will lay two parallel slab tracks.
Service is set to begin at the end of 2009.
By Neil Sandler