 |
| GERCC was used to produce an inexpensive, aesthetically pleasing finish for the non-overflow portions of the downstream face of the 188-foot-high Hickory Log Creek Dam in Canton, Ga. |
Roller compacted
concrete (RCC) is frequently used for the construction of mid-sized to
large mass concrete applications, including dams, because of its faster
placement rate, lower heat of hydration, and reduced cost compared with
conventional concrete. RCC is a no-slump concrete that is typically spread in
lifts as thick as 12 inches with earthmoving equipment and compacted with a
smooth vibratory roller. Early experience on RCC dam applications in the 1980s
showed a tendency for seepage to develop along the 1-foot-thick lift lines due
to the tendency at the time to use a lean RCC mix. Therefore, many RCC dam
designers started including an upstream facing system as a watertight barrier
in combination with careful attention to lift joint preparation and treatment.
The upstream barrier is typically constructed of a zone of conventional
concrete, an exposed liner system, or precast concrete panels with or without a
liner syste
An alternative facing material that has been used
extensively overseas and is starting to gain more widespread acceptance in the
United States is Grout Enriched RCC (GERCC). This innovative process includes
addition of a neat cement grout to the uncompacted RCC at each lift along the
upstream face. After the grout has soaked into the RCC, immersion vibrators are
used to mix and to consolidate the grout and RCC to produce a seamless zone
similar to conventional concrete. The surface of the RCC lift is then compacted
with a vibratory roller.
This process is typically used with higher-paste RCC mixes
with cementitious contents (cement plus Class F fly ash) of 300 pounds or more
per cubic yard and has a Vebe time less than 20 seconds. The grout simply
consists of a mixture of portland cement and water with a 1:1 ratio by weight.
The water-cement ratio of the grout may be reduced with the use of a
water-reducing admixture to approximately 0.7:1.0 to improve the strength and
durability of the GERCC facing. The GERCC facing is typically applied to
produce a facing with thickness between 12 and 24 inches.
Laboratory tests have shown that the grout may not evenly
disperse throughout the RCC by using immersion vibrators. However, the basic
intent for using GERCC is to ensure that enough paste is made available to fill
any voids in the RCC that is placed against formwork and foundation contacts.
Unless the parent RCC mix has an excessively low Vebe time (less than 10
seconds), compacting the RCC against formwork or rock surfaces without the
additional grout results in honeycombing and therefore poor aesthetics of the
finished surfaces and poor bonding to foundation surfaces. The proper
application of GERCC has proven to provide conventional concrete-like surfaces
and good bonding capacity.
 |
| Workers conduct a final cleaning of the GERCC downstream steps in the spillway of the Deep Creek Watershed Dam 5D. |
The first reported use of GERCC for an upstream facing
system was on the cofferdam for Puding Dam in China in 1994. Subsequently,
GERCC was used on the 430-foot-high Jiangya Dam in Hunan Province, China, for
the upstream face and to create a bond along the rock abutment interface.
Placement of the 1,439,000 cubic yards of RCC was successfully completed in
1999. According to a listing of RCC Dams worldwide published in Hydropower and
Dams World Atlas 2010, more than 75 dams have been completed or are currently
under construction using GERCC in at least 22 countries, with 35 constructed in
China alone.
Since its inception, the GERCC process has been used for the
exposed upstream and downstream face of the dam for improved aesthetics, to
bond RCC against rock abutments, for the construction of drainage galleries,
and around conduits and other penetrations through dams. Numerous minor
variations in the process have been developed over the years for various dams.
For example, Grout Enriched Vibrated RCC (GEVRCC) involves placing the grout
along the upstream face of the previously compacted lift of RCC, then spreading
a loose lift of RCC over the grout and using immersion vibrators to draw the
grout up into the RCC. This process typically has been limited to very
high-paste RCC mixes. The most recent development involves placing RCC and
grout into a transit mixer on the lift surface and producing a mixture referred
to as GERCC-M to be deposited in place, consolidated, and compacted.
 |
| Workers apply neat cement grout to the uncompacted RCC at the downstream formwork for the Deep Creek Watershed Dam 5D. |
GERCC has been proven to produce a consistent, economical,
low-permeability upstream face for dams. One of the primary reasons for its
popularity worldwide is that it uses a simplified procedure that can be
performed simultaneously with the RCC placement and does not interfere with
overall RCC production rates. Other facing systems such as precast panels and
conventional concrete require careful coordination and timing so they do not
slow down RCC production. Another advantage is that the grout used in GERCC is
mixed directly with the parent RCC and there is no potential for delamination
at the critical location between the facing material and the RCC mass.
In the United States, the use of GERCC technology has been
fairly limited. This can be attributed to the infrequent construction of new
large dams in the United States, the early general trend to use dryer/leaner
RCC mixes that are less conducive to successful GERCC, and concern over
freeze-thaw durability. Integration of air entraining admixtures into GERCC has
not been successful to date. In addition, the majority of new dams using GERCC
have been constructed in developing countries with inexpensive labor. Since the
GERCC installation process is labor intensive and rates are typically higher in
the United States, this process can be less economical than in other parts of
the world.
The first domestic use of GERCC occurred in 2002 on the
construction of the 309-foot-high Olivenhain Dam for the San Diego County Water
Authority. For this case, GEVRCC was used to produce a relatively smooth
upstream face, suitable for the installation of an exposed membrane liner after
RCC construction was completed, and at the foundation contacts. In 2007, GERCC
was used to produce an inexpensive, aesthetically pleasing finish for the
non-overflow portions of the downstream face of the 188-foot-high Hickory Log
Creek Dam in Canton, Ga.
Deep Creek Dam
The recently completed Deep Creek Watershed Dam 5D represents the first use of
GERCC as the sole upstream barrier for a dam in the United States. This
multi-purpose flood control and water supply dam in Yadkinville, N.C., was
designed by Schnabel Engineering. A composite dam design was selected to make
efficient use of the complex existing foundation conditions. Shallow competent
bedrock on the right side of the valley was used to support a RCC gravity
section with a maximum height of 74 feet and a length of approximately 750
feet. On the left side of the valley, rock was deeper and more variably
weathered. A zoned earthen embankment was designed to wrap around the end of
the RCC dam and extend roughly 800 feet to the left abutment.
During design, Schnabel primarily focused on three types of
RCC facing including formed RCC, conventional concrete, and GERCC. Several
factors were considered in the selection including constructability,
permeability, durability, cost, and appearance. GERCC was selected based on its
proved performance worldwide, lower anticipated cost, and expected production
advantage compared with other facing alternatives. GERCC also offered
flexibility along the dam/abutment and foundation interface where surfaces were
expected to be irregular.
 |
| A vertical core taken of a GERCC facing through an upstream PVC waterstop shows excellent bond and no honeycombing. |
Design of the proposed dam was completed in 2004; however,
due to lack of funding, the project was not bid until October 2008. The project
was awarded to the low bidder, Haymes Brothers Construction Inc. from Chatham,
Va. ASI Constructors Inc. of Colorado was responsible for RCC and conventional
concrete as a subcontractor to Haymes. The project was completed in August 2010
and includes a 16-inch-thick GERCC upstream face and a 12-inch-thick GERCC
downstream face. Since initial filling, the face has performed successfully
with very minimal seepage.
In the United States and its territories, since the
completion of Deep Creek, GERCC has been used to produce an aesthetically
pleasing downstream face for the exposed RCC overtopping protection project at
Fox Creek #4 Dam in Flemingsburg, Ky., and is currently being used for the
upstream and downstream facing for Portuguese Dam in Puerto Rico, designed by
the U.S. Army Corps of Engineers, and at the San Vicente Dam near San Diego
where the existing 220-foot-high concrete dam is being raised 117 feet with
RCC.
Source: CEnews.com